Energy conservation at Eastbourne DGH

By: East Sussex Hospitals NHS Trust

Replacement of plant reaching the end of its useful life

£454,529 (excl. capital charges) (Estimated)

3100 tonnes of CO2 (Estimated)

Replacement of the existing main steam boiler house installing modern high efficiency steam boilers with a 1.0MWe Combined Heat and Power unit sized to match the main site electrical and thermal base loads. The design solution maximises usage of both high and low grade heat from the CHP unit to pre-heat feed water and to support steam production though a combination waste heat and dual fuel boiler.

Eastbourne District General Hospital, Kings Drive, Eastbourne, East Sussex

Reduce carbon emissions and site energy costs

DoH Energy & Sustainability fund
Kier Group, P21 partner

27/07/2008
completed

Staff magazine and intranet

£2.95 million

Maintaining services to the hospital whilst decomissioning the old plant and installing and commissioning the new

David Philliskirk, Director of Estates and Facilities, david.philliskirk@esht.nhs.uk, 01424 755470 ext 8818